Why Can Two Solar Projects Cost Differently Even When They Use the Same Equipment?

The Real Cost of a Solar Project · Part 2 of 29 – solar site survey

Quick answer: A solar site survey is the on-site check an EPC carries out before it designs and prices a commercial solar plant. It covers six areas: documents, the roof, shading and dust, the electrical room, cable routes, and how the site runs and is accessed. Anything it doesn’t verify becomes an assumption inside the price.

In Part 1, two EPC companies quoted for the same 1 MWp factory roof, and their prices didn’t match. Both proposals said “site survey completed”. EPC A spent a morning on the roof. EPC B spent a full day on the roofs and in the electrical room with the plant electrician.

Why does a site survey decide so much of the price?

A quotation can only price what the EPC knows. Whatever the survey doesn’t check has to be assumed: that the roof is sound, that an LT panel has a spare feeder, that the cable route is short. If the site later disagrees, the result is a variation during execution, or lower generation.

What does a structured solar site survey check?

  1. Documents. Twelve months of bills, the single-line diagram, transformer and generator details, drawings and any interval load data. They tell the team what to verify on site.
  2. The roof. Usable area, not total area: skylights, vents, gutters and edge setbacks come out of it. The team records sheet profile, fasteners, corrosion and purlin spacing, and maps fragile skylights for safety.
  3. Shading and dust. Parapets, tanks, chimneys, nearby buildings and trees, with heights and distances, because a shadow that misses the roof in June can cross it in December. Nearby dust sources set the cleaning frequency.
  4. The electrical room. Transformer loading, spare feeders in each LT panel, the metering point, existing earthing, and any diesel generators, which may need a controller so solar stays within their safe limits.
  5. Cable routes. The real route from roof to connection point is walked and measured, along with locations for inverters, distribution boards and earth pits.
  6. Operations and access. Shifts, weekly offs and expansion plans, plus roof access, crane space, storage, a water point for cleaning and permit rules.

How do survey findings change the price?

Survey finding

Possible cost impact

Fragile skylights and open edges

Walkways, lifelines and skylight protection

Corroded sheeting

Repair or re-sheeting before installation

No spare LT feeder

A new distribution board or panel works

Diesel generators on site

A solar–generator controller

Longer cable route

More cable, trays and labour

No water point on the roof

A cleaning water line

A finding priced at quotation stage is easier to handle than the same finding discovered after the order.

Does “site survey completed” always mean the same thing?

No. A light survey uses drawings, a roof walk and photos. It is quick, and often enough for a budgetary price. A structured survey measures the roof, visits the electrical room, walks the cable route, and ends with a report and an assumptions list.

On our hypothetical reference factory, the structured survey found spare capacity on only one of two LT panels, two diesel generators and a 120 m cable route. EPC A assumed spare capacity; EPC B priced new distribution boards. Neither was wrong. They priced different levels of certainty.

solar site survey

What should you ask your EPC before the survey?

  1. Will engineers visit the electrical room as well as the roof?
  2. How will the roof be measured: from drawings, by laser or by drone?
  3. Will skylights, roof edges and cable routes be mapped and measured?
  4. Will we receive the survey report, with photos and an assumptions list?

Next part: from site data to engineering inputs

A survey produces measurements, photos and notes: raw data, not a design. Part 3 shows how an EPC turns them into the design basis every later calculation uses.

Next Part: From Site Data to Engineering Inputs — How an EPC Company Analyses a Solar Project

Frequently asked questions

How long does a solar site survey take?

It depends on the number of roofs, access and the electrical system. For a factory rooftop, a structured survey can take a full working day on site.

Can an EPC quote without a site survey?

It can give a budgetary estimate. A firm price needs the roof, electrical room and cable routes verified, or the gaps listed as assumptions.

Is a drone survey enough?

Drones speed up roof mapping, but sheeting, fasteners and the electrical room still need checking in person.

About Solluz Energy